Project Milestones

Nord Stream is one of the most advanced infrastructure projects of its scale meeting all international standards applicable. Safe and efficient implementation of the project is possible only with professional experience and commitment of Nord Stream shareholders, partners and staff.

Project on Track - Present Situation

Completed

  • Feasibility study
  • General technical design
  • EIA programme
  • Public consultations under the Espoo process
  • Contracting of pipe production and pipe-laying contracts
  • Route optimisation, additional surveys
  • Permitting process

 

Ongoing

  • International consultations
  • Detailed technical planning
  • Financial concept
  • Dialogue with authorities and public in the Baltic Sea region
Nord Stream Project Milestones (Click to enlarge)

Milestones

1997-1999

Feasibility Study: International engineering companies, Russian research institutes and the Russian-Finnish company North Transgas Oy conducted surveys and maritime research in the Baltic Sea. Alternative routes for transporting Russian gas to Europe were investigated during that time. A feasibility study of the offshore section confirmed the technical feasibility and economic efficiency of a pipeline through the Baltic Sea.

2000

Project of Interest: In December, the European Union designated the offshore pipeline a “Project of Interest” as part of the Trans-European Energy Networks (TEN-E) guidelines.

2005

Establishment of the North European Gas Pipeline Company: In September, OAO Gazprom, BASF SE and E.ON AG signed a general agreement on the construction of the pipeline. The North European Gas Pipeline Company (later renamed Nord Stream AG) was established in December.

2006

Start of Approval Process: The European Union reconfirmed the importance of Nord Stream by listing it as a “Project of European Interest” within the Trans-European Energy Networks (TEN-E) guidelines. In November, Nord Stream submitted a Project Information Document on the planned pipeline to the responsible environmental authorities, in accordance with the Espoo Convention.

2007

Detailed technical planning and environmental assessment studies: Nord Stream submitted permit applications  to the Swedish government.

2008  

Conclusion of contracts:  All major contracts with suppliers were finalised: Dutch gas infrastructure company N.V. Nederlandse Gasunie joined the Nord Stream consortium.

2009

Transboundary Environmental Impact Assessment and first permits: The final transboundary EIA report was published for public consultation on 9 March. On 20 October, Nord Stream received the approval from Denmark’s Energy Authority to construct the pipeline in Danish waters. On 5 November, Sweden and Finland granted permits to utilise their Exclusive Economic Zones (EEZ) for the pipeline. At the end of December Germany and Russia issued the two necessary permits for the pipeline’s construction.

2010

Finalisation of permitting process and laying of Pipeline One: On 12 February Nord Stream received the last of the permits required to start constructing the pipeline from the Regional Administrative Agency for Southern Finland. Construction of the first line started in April of 2010.  In June, French energy provider GDF Suez S.A. joined the Nord Stream consortium.

2011

Commissioning of Pipeline One: After thorough testing, gas deliveries will start.

2011-2012  

Laying of Pipeline Two: A second pipeline, running parallel to the first, will be built.

2012

Commissioning of Pipeline Two: With the second line coming on stream, the full capacity of 55 bcm per year will be reached in 2012.


Please find more information on that topic in our e-FACTS magazine:



Shortcut: Information Library

Information on Nord Stream and more
> Click here

Newsletter 0: Key Facts

Basic information about Nord Stream
> Study

Shortcut: Permitting

Nord Stream and national permitting processes
> Click here

Paper: Espoo Report

Non-Technical Summary of Espoo Report
> Click here

©2010 Nord Stream | Disclaimer