Pressure Testing Step 4: Pressurising Section Three

Once sections one and two have been tested, the Far Samson moves to KP 675 to flood, clean and gauge section three. Pressurisation and monitoring of this section is performed from the German landfall. Meanwhile, sections one and two will be connected underwater.