Oct. 21, 2010 | Berlin | Nord Stream AG, headquartered in Zug, Switzerland, is the winner of the 2010 German Logistics Award of the German Logistics Association (BVL). The jury selected the company in recognition of its project "Logistics for the Pipeline", i.e. the logistics for the Nord Stream gas pipeline through the Baltic Sea from Wyborg, Russia, to Lubmin near Greifswald, Germany. The award ceremony took place in Berlin within the scope of a gala event held on the evening of the first day of the 27th German Logistics Congress, which takes place from October 20 to 22.

In his speech, Professor Hans-Olaf Henkel, the chairman of the jury, summarised the reasons for awarding Nord Stream with the prestigious prize: "The magnitude of the project is gigantic. Huge amounts of material had to be procured from the world market and transported. By placing production hubs at the beginning and end of the large building site, material flows were minimised. Thanks to the infrastructure expansion in the ports, the use of the means of transport was optimised, and the handling overhead was streamlined as far as possible. Short routes reduced the building site traffic. Emissions were cut. Methods and techniques from other industries were smartly adapted. The error rate in the material supply was zero, and so far, the assembly has not been interrupted. New jobs have been created in regions with a weak economic structure and will most likely continue to be available on a long-term basis, as other large orders will follow after the end of the project. The company showed courage in making unusual decisions and was highly target-oriented. With a great majority, the jury elected the project as exemplary and worthy of the award."

The Winner

Nord Stream AG is the youngest winner on the list of companies recognised for their logistics concept since 1984. Nord Stream was established as Nordeuropäische Gasleitungs-Gesellschaft on December 2, 2005 and was renamed Nord Stream AG in October 2006. The shareholders of Nord Stream are the Russian Gazprom with 51 percent, BASF SE/Wintershall Holding GmbH and E.ON Ruhrgas AG with 15.5 percent each, and the Dutch N.V. Nederlandse Gasunie and the French GDF SUEZ S.A. with 9 percent each. Following its commissioning, Nord Stream will operate the pipeline. The task of Nord Stream AG is to plan, build, and operate the gas pipeline through the Baltic Sea, thereby connecting the world's largest natural gas reserves in Russia with the European gas grid. This pipeline consists of two parallel lines of 1,224 kilometres each. The first line with a transport capacity of approximately 27.5 billion cubic metres (bcm) a year is to go live in 2011. Upon completion of the second line in 2012, the transport capacity is to be doubled to approximately 55 bcm. 55 bcm means about one tenth of the current demand for natural gas in the EU. The investment volume of 7.4 billion euros for the construction of the pipeline includes a logistics budget of 650 million euros.

Project Volume

The two lines require 2 x 100,000 pipe segments of an average length of 12.2 metres and an outer diameter of approximately 1.4 metres. The total weight of the steel of which the pipes consist amounts to 2.2 million tonnes (1.6 million tonnes from Germany, 0.5 million tonnes from Russia, and 0.1 million tonnes from Japan). Along with the inner and outer corrosion protection coating and an additional concrete layer, the total weight amounts to 4.6 million tonnes. Taking into account the heavy concrete layer consisting of cement (0.4 million tonnes from Germany), magnetite (1.45 million tonnes from Sweden), and sand/split (0.4 million tonnes from Norway and Finland) for secure fastening on the seabed, the material to be moved with all transports and handling operations totals 90 million tonnes. The optimised supply chain with 30 participating companies from 10 countries necessitates custom-tailored building logistics.

Central Logistical Issues

  1. Are the port capacities adequate? Is the port space sufficient? 800 kilometres of finished products are required for to keep the laybarges supplied with pipes for construction. For this, the total area must amount to 100-150 ha. 68 ports were checked as locations. From these, 18 were singled out, then 9, and finally 5. Additionally, 20 field storage sites were defined. The decisions were made on the basis of ecologic and economic criteria, not according to political aspects.
  2. Which pipe supplier supplies what type of pipes in what coating state to where? Who applies which coating, where and when?
  3. Which locations need to be selected to optimise the transport routes?

An Innovative, Courageous Concept Instead of using the existing concrete coating plants in Norway and Scotland, two new production facilities were built in Kotka, Finland, and in Mukran on the Island of Rügen, Germany. This enabled savings of 60 million euros for transport costs. Pipe storage sites were set up close to the plants. Today, additional pipe storage sites exist in Hanko, Finland, Slite in Gotland, Sweden, and in Karlskrona, Sweden. Though this was the most suitable solution from the geographical and logistical perspective, a number of obstacles had to be overcome: the Slite port in Gotland was not deep enough, the pier was too narrow, its load capacity was insufficient, and the storage space was inadequate for loading pipes in the carrier vessels.

What to do? The just-in-time approach that is common in the automotive industry was adapted for the large pipes of 20-30 tonnes, namely from ship-to-ship: in Slite, pipes supplied from Mukran by ship are directly transferred to a transportation vessel on the other side of the pier. In this way, 55,000 pipes are directly trans-shipped via the pier in Slite. This amounts to about one fourth of all pipe segments.

Due to this logistics concept, every point of the pipeline is less than 100 nautical miles from the next storage site; all supply tours can be completed within 24 hours (round-trip). Three special carriers are being used. Additionally, a certain number of pipes is kept on the pipelay vessels as reserve, so that the work does not need to be interrupted if a carrier is not available

Background

With the German Logistics Award, BVL honours practically applied logistics concepts that may be submitted by companies from the industry, commerce, and service sector. The documents to be assessed by the jury must present the development of the concept, the implementation, and the results. The practical application is vital. The German Logistics Association initiated the award in 1984. The winners of the past five years were the Würth Group, Künzelsau (2009), Deutsche Lufthansa AG together with Fraport AG, Frankfurt (2008), CLAAS KGaA mbH, Harsewinkel (2007), Bosch und Siemens Hausgeräte GmbH, Fürth (2006), and Kühne + Nagel International AG, Schindellegi (2005).